June 5, 2018 8:00 AM

Road Work Alert

3 NOTICES TO RESIDENTS OF TOWN OF BOONTON

NOTICE 1: RVRSA ROAD WORK

On or about Tuesday, June 5, through Friday, June 15, Morris Avenue, between Main Street and Rockaway Street, may be subject to partial (1-way) or full closure for utility work. It is currently anticipated that full closures (both directions) may be necessary on June 6-8 and 11-12. One way closure (closure at Main Street) may be necessary on June 5 and 13-15. Detour signs and traffic control will be effected to help guide motorists.

NOTICE 2: MYRTLE & WOOTTON

Road Paving Myrtle Ave/Wootton St on or about June 7th from from 9p-4a will require lane closures, detours will be posted, but will be subject to change as work progresses. It will be best to avoid area.

Thru traffic heading southbound coming from the Montville area can utilize Vreeland Ave to Lathrop Ave to Main St

Thru traffic heading northbound coming from Boonton to the Montville area can utilize Main St to Lathrop Ave to Vreeland Ave

Westbound traffic can utilize Main St in Boonton or Taylortown Rd in Montville via Boonton Ave to access Wootton St above Myrtle Ave. Wootton St below Myrtle will be best accessed by Vreeland or Main St to Lathrop Ave to Wootton St


NOTICE 3: JOHN HILL SCHOOL - SAFE ROUTES TO SCHOOL IMPROVEMENTS

On or about Friday, June 22nd D&L Paving Contractors will mobilize to begin construction of pedestrian safety improvements at John Hill School, nearby intersections, and crosswalks. This work will occur in the following four (4) limited work areas on or about the tentative dates indicated, weather permitting:
1. Monroe Street between Roosevelt Avenue and Reservoir Drive
a. June 25th to July 3rd – construction of concrete sidewalks and paving of rear student drop-off zone on north side of Monroe Street. Construction of concrete sidewalk, retaining wall and steps on school property.
b. July 9th and 10th – installation of striping, railings and fencing on school property.
2. Intersection of Lathrop Avenue and Vreeland Avenue
a. June 25th and 26th – construction of concrete sidewalks, ADA-accessible ramps and Belgium block curbs for crosswalk improvements.
b. July 9th and 10th – installation of crosswalk striping at intersection.
3. Intersection of Lathrop Avenue and Washington Street / Main Street
a. June 25th and 26th – construction of concrete sidewalks, ADA-accessible ramps, and concrete curbs for crosswalk improvements.
b. July 9th and 10th – installation of crosswalk striping at intersection.
4. Lathrop Avenue at John Hill School Entrance
a. June 25th and 26th – construction of concrete sidewalks, ADA-accessible ramps, and concrete curbs for crosswalk improvements.
b. July 9th and 10th – installation of crosswalk striping at intersection.
c. July 9th to 13th – installation of pedestrian crossing safety lighting and signage.
The week of July 9th, D&L Paving will address site restoration, stabilization, and clean up of all work areas.
We apologize for any inconveniences to residents as a result of this construction. We appreciate your cooperation and support of this project to improve pedestrian access to John Hill School for the safety of all students and residents.
D&L Paving Contractors

Road Work Sign